Dauphine Avenue Water Main Improvements - 2022

General Information

Completion DateSeptember 16, 2022
Project ManagerMichael Weller, 847-664-4132
ContractorHoliday Sewer & Water Construction, Inc., 847-526-3788
Awarded Contract Amount$475,000
Funding SourcesBonds


Special Note - Receive E-mail Updates About This Project

The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the projects.  If you are interested, please subscribe at this link. Updates will begin when the project commences in May 2022.
 

Project Description

This project will focus on the replacement of the original 1960's water main along Dauphine Avenue (from 3856 Dauphine Avenue to Charlemagne Drive).
 

Enabling Resolution:

A full description of the project can be found as part of Resolution 2022-39, which awarded the project to the Village's contractor.
 

Construction Notification Letters:

The Village will be mailing initial construction notices to all residents with homes that are located in the project's vicinity. Residents with homes that require a new water service line and shut off box received information about the potentials of the planned work. Future updates will be posted here as they become available.
 

Project Contacts

For questions regarding this project, please contact Michael Weller, Project Manager. Mr. Weller can be reached at 847-664-4132 or via the GONorthbrook system.
 

Current Project Updates

April 11, 2022

Work on this project is anticipated to begin in May 2022. Future updates will be posted here as they become available.