Dehne Road/Glendale Avenue Stormwater Project - 2018

General Information

Tentative Completion Date Wednesday, October 31, 2018 (tentative)
Project Managers Village Staff (To Be Named)
Contractor A Lamp Concrete Contractors
Award Contract Amount $513,880 (all stormwater projects for FY 18/19)
Funding Sources Bonds

Special Note - Receive E-mail Updates About This Project


The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is availlable to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2018.


Project Description

This project involves increasing the swale capacity between Dehne Road and Glendale Avenue and the adjacent properties near this intersection. This project also involves removing and replacing 350 feet of old 8-inch corrugated storm sewer pipe and inlets located on the east side of Glendale Road and constructing a 330 foot, 18-inch storm sewer along Glendale Avenue between Bellevue Place and Techny Road. Currently, this intersection experiences flooding of the roadway and parkway.

Enabling Resolution


A full description of the project can be found as part of Resolution 2018-91, which awarded the project to the Village's contractor.

Project Contacts


Project contacts will be announced once the contract for this project has been awarded. If you have questions, you may contact the Village by telephone at 847-272-4711 or via the GONorthbrook system

Project Locations

The project will be limited to the intersection of Dehne Road and Glendale Avenue, adjacent properties and properties along Glendale between Bellevue Place and Techny Road. Final maps and more details will become available once the project is awarded.

Current Project Updates

November 9, 2018 


This week, the Village’s contractor continued ditch-grading work on Glendale Avenue. 

Previous Project Updates

October 26, 2018  

Next week, crews will continue ditch grading and final restoration work on Glendale Avenue.

October 5, 2018  

This week, the Village’s contractor completed storm sewer installation and asphalt pavement patching on Glendale Avenue.


September 28, 2018  

This week, the Village’s contractor continued placing new storm sewer on the west side of Glendale Avenue from Bellevue Place to Asbury Road (pictured right). Next week, staff anticipates that crews will continue placing storm sewer on Glendale and begin patching any asphalt pavement and repairing any driveways that were disturbed by project activities.


September 21, 2018  

This week, the Village’s contractor began placing storm sewer on the west side of Glendale Avenue. Next week, it is anticipated Nicor will complete the two gas main relocations on Woodlawn Road which will clear the way for the project to continue on Woodlawn. 


September 14, 2018  

This week, the Village’s contractor notified staff that it plans to begin tree root pruning and placing storm sewer on Glendale Avenue next week. This project involves increasing the swale capacity between Dehne Road and Glendale and replacing storm sewer on Glendale to mitigate flooding.


August 10, 2018  

On Wednesday, August 8, the Village held a pre-construction meeting with representatives from the Village’s Police, Fire, and Public Works Departments as well as representatives from Commonwealth Edison, Nicor, and the Village’s contractor to discuss coordination for the upcoming construction. Staff will continue to work with the utility companies to mitigate any potential conflicts before beginning work. 


August 3, 2018

This month, the Village will begin construction of three stormwater management projects: Woodlawn Road, Dehne Road and Glendale Avenue, and Elm Ridge Drive culvert replacement. On Thursday, August 2, the Village held an Open House for residents to share information on the scope of work and timelines for each project. Staff anticipates work will begin early to mid-August and be completed in November.

July 27, 2018 - Construction/Open House Announcement

Next month, the Village will begin the construction of three stormwater management projects: the Woodlawn Road Project, the Dehne Road and Glendale Avenue Project, and the Elm Ridge Drive culvert replacement. This week, the Village delivered letters to residents living near the construction areas notifying them of the project and inviting them to an Open House on Tuesday, August 2, from 5:30 p.m. to 7:00 p.m. at Village Hall. Staff anticipates work will begin early to mid-August and end in November 2018.


January 8, 2018 - Work Announcement

At this time, staff anticipates work on this project will begin summer 2018. For more details, see the Village's Fiscal Year 2018/2019 Capital Improvement Plan