Concrete Street Panel Replacement - 2019

General Information

Tentative Completion Date October 31, 2019
Project Manager Nailah Walters, Project Manager
847-664-4132
Contractor Triggi Construction
Awarded Contract Amount $457,215
Funding Sources Bonds

2019 Construction Map


This project is one of a number of different construction projects occurring in the Village in 2019. To learn more about other projects and see a map, please see the 2019 Construction Interactive Map.



Special Note - Receive E-mail Updates About This Project

 
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is availlable to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2019.


Project Description


The Village of Northbrook proactively reviews the condition of its streets on a regular basis to identify problems and appropriate measures to correct them. This project involves panel replacement in the Heathercrest East subdivision.

Enabling Resolution

At its Tuesday, June 25 meeting, the Village Board approved Resolution 2019-96, which awarded this project to Triggi Construction of West Chicago, Illinois. More details about this project can be found in the Resolution.

Project Notices

The following notices have been issued for this project:

Project Locations


This project will focus panel replacement on Fern Avenue, Heather Lane, Barberry Road, Smith Road, Lilac Lane, Aspen Road and Clover Road. A map of the locations can be found at this link.

Current Project Update

September 13, 2019


This week, the Village’s contractor began restoration work. Next week, crews will continue restoration.

Previous Project Updates


September 6, 2019

This week, the Village’s contractor completed pouring new concrete pavement and next week will begin restoration.


August 30, 2019

This week, the Village’s contractor completed pouring new concrete pavement and next week will begin restoration.


August 23, 2019

The Village’s contractor continued pouring new concrete pavement and will continue this same work next week. Motorists are asked to use caution in the work area and to expect full lane closures as the project progresses. 


August 16, 2019

This week, the Village’s contractor continued pouring new concrete pavement. Next week, crews will continue this same work. Motorists are asked to use caution in the work area and to expect full lane closures as the project progresses. 


August 9, 2019

This week, the Village’s contractor began pouring new replacement concrete street pavement. Next week, crews will continue removing and replacing pavement. Motorists are asked to use caution in the work area and to expect full lane closures as the project progresses.


August 2, 2019

This week, the Village’s contractor began pavement removals in anticipation of pouring new concrete. Next week, crews will continue removing and replacing pavement. Motorists are asked to use caution in the work area and to expect full lane closures as the project progresses. 


July 19, 2019

The Village’s contractor will begin the Heathercrest East panel replacement project next week, weather permitting. The initial work for this project will include saw cutting of the roadway in preparation for removal. Motorists are asked to use caution in the work area and to expect full lane closures as the project progresses.


June 25, 2019 - Contract Award

At its Tuesday, June 25 meeting, the Village Board approved Resolution 2019-96, which awarded this project to Schroeder & Schroeder, Inc. of Skokie, Illinois. More details about this project can be found in the Resolution.


December 19, 2018 - Work Announcement

Details and time schedules for this project will be announced in April 2019.