Brittany Road Stormwater/Water Main Combined Project - 2020

General Information

Tentative Completion Date Wednesday, October 31, 2020 (tentative)
Project Managers Jeff Koza, Capital Projects Manager, 847-664-4124
Contractor Lenny Hoffman Excavating, Inc. 
Award Contract Amount $1,083,382 (combined cost for all 2020 stormwater capital projects)
Funding Sources Bonds

Special Note - Receive E-mail Updates About This Project

 
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2020.


Project Description

This project involves supplementing the existing 42-inch storm sewer on Brittany Road by constructing approximately 375 feet of 48-inch storm sewer to drain the low area on the street to the 48-inch storm sewer outlet on Bordeaux Road. The inlets within the low area will connected to that new storm sewer and new inlets will added. Additionally, a downstream structure will be added to help control the flow of flood water.

As part of this work, the existing 450 feet of water main located on Brittany Road between Bordeaux and Dauphine will also be replaced. 

Enabling Resolution

 
On Tuesday, June 9, the Village Board approved Resolution 2020-78, which awarded the construction contract to Lenny Hoffman Excavating, Inc. 

Construction Notice

On Thursday, June 11, the Village issued initial construction notices to all potentially impacted properties for this project. A copy of this notice may be found at this link

Project Contacts


Project contacts for this project is Jeff Koza, Capital Projects Manager. Mr. Koza may be reached at 847-664-4124 or jeff.koza@northbrook.il.us. If you have any other questions, you may contact the Village by telephone at 847-272-4711 or via the GONorthbrook system

Project Locations

The project will be limited to Brittany Road between Bordeaux and Dauphine. 

Project Updates


September 21, 2020

The contractor has advised they plan to be on site Monday (9/21) placing concrete pavement on the south side of Brittany Road. This concrete will need approximately one (1) week to cure to gain sufficient strength before the road can be opened. After completion of concrete paving on Brittany Road the Contractor will complete staged pavement repairs at the intersection of Bordeaux and Brittany as well as begin parkway restoration work on Brittany Road.


August 21, 2020

Thank you for your continued patience as work on Brittany Road between Bordeaux Drive and Dauphine Avenue progresses. Currently the new storm sewers are installed. The new water main has been installed and passed all tests. The last new water service line will be transferred from the old water main to the new water main by the end of today. Only two connections of the new water main to the existing water system remain (scheduled for Monday and Tuesday) and then all underground work will be completed.

Next week the contractor will complete sidewalk repairs on the block and then begin pavement reconstruction. The road will be reconstructed one half at a time. With each half taking roughly 10 to 14 days to complete (depending on weather). While one half is being reconstructed there will be one lane of one way traffic provided for residents but the road will remain closed to thru traffic. During the work day while the road is being reconstructed there will be construction trucks on the one open lane of traffic blocking the road. So residents will experience delays due to the construction traffic. After the first half of the road has been constructed and the concrete has cured long enough to support traffic work on the other side of the road will begin. After both sides of the road have been reconstructed the road will be re-opened to traffic and last work item which is parkway restoration work will begin.

A written notice will be provided to the residents living within the reconstruction limits next week. The notice will contain additional information about driveway access restrictions. Should you have any immediate project needs/concerns please contact the consultant project manager Syed Ahmed from Atlas Engineering Group at 224-795-3809. Should you have any general comments or concerns feel free to contact Jeff Koza, PE, Capital Projects Manager, at Northbrook Public Works 847-664-4124.

June 11, 2020 - Open House Announced

On Thursday, June 11, the Village mailed initial notices for this project and announced a virtual Open House would be held on Thursday, June 25. Details of how to attend the Open House will be posted in the near future. 



June 10, 2020 - Work Award

On Tuesday, June 9, the Village Board approved Resolution 2020-78, which awarded the construction contract to Lenny Hoffman Excavating, Inc. 



January 27, 2020 - Work Announcement

This project is scheduled to begin in the summer of 2020. More details will be posted as they become available.