Longvalley Drive Stormwater Project - 2019

General Information

Tentative Completion Date Monday, November 11, 2019
Project Managers Aram Beladi, Project Manager,
847-664-4133
Contractor H. Linden & Sons
Award Contract Amount $644,030 (Dehne, Blackthorn, and Longvalley projects)
Funding Sources Bonds

2019 Construction Map


This project is one of a number of different construction projects occurring in the Village in 2019. To learn more about other projects and see a map, please see the 2019 Construction Interactive Map.



Special Note - Receive E-mail Updates About This Project

 
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is availlable to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2019.



Project Description

This project involves the replacement of 300 feet of stormwater sewer at the intersection of Longvalley Drive and Longvalley Court to improve drainage collection system's capacity.

Enabling Resolution

 

At its Tuesday, July 23 meeting, the Village Board approved Resolution 2019-106, which awarded this project to H. Linden & Sons of Plano, Illinois. More details about this project can be found in the Resolution.

Project Contacts

 
For questions regarding this project, please contact Aram Beladi, Project Manager. Mr. Beladi can be reached at 847-664-4133 or via the GONorthbrook system.

Project Locations

The project will be limited to the intersection of Longvalley Drive and Longvalley Court.

Project Updates

November 11, 2019

As of Monday, November 11, this project is substantially complete. The Village thanks local residents for their patience and cooperation during this work.


October 18, 2019

This week, the Village’s contractor began concrete restoration work on Longvalley Drive. Next week, crews will complete any necessary asphalt restorations.


October 4, 2019

Next week, crews begin work on the Longvalley Drive project, which includes replacement of existing inlet structures and the addition of a new inlet at the intersection of Longvalley Drive and Longvalley Court.



December 27, 2018 - Work Announcement

This project is scheduled to begin in the summer of 2019. More details will be posted as they become available.