Longvalley Drive Stormwater Project - 2019
General Information
Tentative Completion Date | Monday, November 11, 2019 |
Project Managers | Aram Beladi, Project Manager, 847-664-4133 |
Contractor | H. Linden & Sons |
Award Contract Amount | $644,030 (Dehne, Blackthorn, and Longvalley projects) |
Funding Sources | Bonds |
2019 Construction Map
This project is one of a number of different construction projects occurring in the Village in 2019. To learn more about other projects and see a map, please see the 2019 Construction Interactive Map.
Special Note - Receive E-mail Updates About This Project
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is availlable to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2019.
Project Description
This project involves the replacement of 300 feet of stormwater sewer at the intersection of Longvalley Drive and Longvalley Court to improve drainage collection system's capacity.Enabling Resolution
At its Tuesday, July 23 meeting, the Village Board approved Resolution 2019-106, which awarded this project to H. Linden & Sons of Plano, Illinois. More details about this project can be found in the Resolution.
Project Contacts
For questions regarding this project, please contact Aram Beladi, Project Manager. Mr. Beladi can be reached at 847-664-4133 or via the GONorthbrook system.
Project Locations
The project will be limited to the intersection of Longvalley Drive and Longvalley Court.Project Updates
November 11, 2019
As of Monday, November 11, this project is substantially complete. The Village thanks local residents for their patience and cooperation during this work.
October 18, 2019
This week, the Village’s contractor began concrete restoration work on Longvalley Drive. Next week, crews will complete any necessary asphalt restorations.
October 4, 2019
Next week, crews begin work on the Longvalley Drive project, which includes replacement of existing inlet structures and the addition of a new inlet at the intersection of Longvalley Drive and Longvalley Court.
December 27, 2018 - Work Announcement
This project is scheduled to begin in the summer of 2019. More details will be posted as they become available.-
Public Works
Physical Address
655 Huehl Road
Northbrook, IL 60062
Phone: 847-272-4711Fax: 847-272-3629Emergency: 847-564-2060 (After Hours Police Non-Emergency Number)
Office Hours
Monday - Friday
7 a.m. - 3 p.m.
(No deliveries after 2 p.m.)
After-Hours Emergencies
Please call the Police Department's non-emergency line at 847-564-2060 for after hours emergencies including water main breaks, leaking meters, sewer back-ups or flooding.
Submit a Question or Service Request
Sign Up for Road Construction E-mail Updates