Second Street Culvert Replacement - 2019

General Information

Tentative Completion Date Wednesday, October 31, 2019 (tentative)
Project Managers Village Staff (To Be Named)
Contractor To Be Determined
Award Contract Amount $288,000
Funding Sources Bonds

Project Description

This project involves the replacement of a culvert located on Second Street as well as improvements to the areas immediately east and west of the culvert. The work to the east will include replacing an existing pipe with an improved design. The work to the west will include removing an existing pipe with poor drainage and returning that area to return to open channel.

Enabling Resolution

 
The enabling resolution to award the contract for this project will be posted after award.

Project Contacts


Project contacts will be announced once the contract for this project has been awarded. If you have questions, you may contact the Village by telephone at 847-272-4711 or via the GONorthbrook system

Project Locations

The project will be limited to the 2100 block of Second Street.

Project Updates

December 27, 2018 - Work Announcement

This project is scheduled to begin in the summer of 2019. More details will be posted as they become available.