Surrey Lane Stormwater Project - 2020

General Information

Tentative Completion Date Wednesday, October 31, 2020 (tentative)
Project Managers Jeff Koza, Capital Projects Manager, 847-664-4124
Contractor Lenny Hoffman Excavating, Inc. 
Award Contract Amount  $1,083,382 (combined cost for all 2020 stormwater capital projects)
Funding Sources Bonds

Special Note - Receive E-mail Updates About This Project

 
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is availlable to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2020.


Project Description

This project involves constructing stormwater improvements at the Surrey Lane cul-de-sac, including a conveyance storm sewer from the cul-de-sac to the Lee Road existing storm sewer and a low/flood overflow structure at the east side of the Surrey Lane cul-de-sac with a restrictor plate. Also, a relief swale will be constructed within the drainage easement. Two inlets will be added within the cul-de-sac area to improve drainage. A short segment of the Lee Road storm sewer system will be modified to accommodate the new storm sewer and flood overflow path. Currently, this area experiences cul-de-sac, front yard and rear yard flooding.

Enabling Resolution

 
On Tuesday, June 9, the Village Board approved Resolution 2020-78, which awarded the construction contract to Lenny Hoffman Excavating, Inc. 

Construction Notice

On Thursday, June 11, the Village issued initial construction notices to all potentially impacted properties for this project. A copy of this notice may be found at this link

Project Contacts


Project contacts for this project is Jeff Koza, Capital Projects Manager. Mr. Koza may be reached at 847-664-4124 or jeff.kzoa@northbrook.il.us. If you have any other questions, you may contact the Village by telephone at 847-272-4711 or via the GONorthbrook system

Project Locations

The project will be limited to Surrey Lane. More details will be announced after the contract for this project has been awarded.

Project Updates

June 11, 2020 - Open House Announced


On Thursday, June 11, the Village mailed initial notices for this project and announced a virtual Open House would be held on Thursday, June 25. Details of how to attend the Open House will be posted in the near future. 


June 10, 2020 - Work Award


On Tuesday, June 9, the Village Board approved Resolution 2020-78, which awarded the construction contract to Lenny Hoffman Excavating, Inc. 


January 27, 2020 - Work Announcement

This project is scheduled to begin in the summer of 2020. More details will be posted as they become available.