Wendy Drive Stormwater Project - 2020
General Information
Tentative Completion Date | Wednesday, October 31, 2020 (tentative) |
Project Managers | Jeff Koza, Capital Projects Manager, 847-664-4124 |
Contractor | Lenny Hoffman Excavating, Inc. |
Award Contract Amount | $1,083,382 (combined cost for all 2020 stormwater capital projects) |
Funding Sources | Bonds |
Special Note - Receive E-mail Updates About This Project
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is availlable to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2020.
Project Description
This project involves installation of inlet structures along Wendy Drive and the replacement of the existing storm sewer with a higher capacity main.
Enabling Resolution
On Tuesday, June 9, the Village Board approved Resolution 2020-78, which awarded the construction contract to Lenny Hoffman Excavating, Inc.
Construction Notice
On Thursday, June 11, the Village issued initial construction notices to all potentially impacted properties for this project. A copy of this notice may be found at this link.Project Contacts
Project contacts for this project is Jeff Koza, Capital Projects Manager. Mr. Koza may be reached at 847-664-4124 or jeff.kzoa@northbrook.il.us. If you have any other questions, you may contact the Village by telephone at 847-272-4711 or via the GONorthbrook system.
Project Locations
The project will be limited to Wendy Drive. More details will be announced after the contract for this project has been awarded.Project Updates
November 30, 2020
This project is now substantially complete.
October 30, 2020
Asphalt pavement repairs planned for this week were delayed due to cold weather. The work was rescheduled and is now expected to begin on Tuesday, November 3.
October 26, 2020
The Contractor has advised they anticipate completing pavement repairs on Ridge Rd and Wendy Dr this week. The project underground utility work is complete at this time. After the pavement is restored clean up and parkway restoration work will be performed.
October 2, 2020
The Village's Contractor has adised they expect to resume work on Wendy Drive on Monday, October 5 (weather dependent). September 21, 2020
During construction of the new storm sewer on Wendy Drive the Contractor encountered sewer lines in conflict with the new storm sewer. Unfortunately, the conflicting sewers could not be adjusted lower and out of the way as originally planned. While the project team was working hard to develop revised plans to resolve these issues, the Contractor had to stop work on the project. Late last week the project designer, working closely with Village Staff, developed a suitable solution to the conflicts. The Contractor has begun ordering new storm sewer structures that are needed to complete the work. These materials will take a week or two to be made and arrive on site. The Village fully expects to be able to resume the project early next month and complete the project. Thank you for your patience while we work through these issues.
June 11, 2020 - Open House Announced
On Thursday, June 11, the Village mailed initial notices for this project and announced a virtual Open House would be held on Thursday, June 25. Details of how to attend the Open House will be posted in the near future.
June 10, 2020 - Work Award
On Tuesday, June 9, the Village Board approved Resolution 2020-78, which awarded the construction contract to Lenny Hoffman Excavating, Inc.
January 27, 2020 - Work Announcement
This project is scheduled to begin in the summer of 2020. More details will be posted as they become available.-
Public Works
Physical Address
655 Huehl Road
Northbrook, IL 60062
Phone: 847-272-4711Fax: 847-272-3629Emergency: 847-564-2060 (After Hours Police Non-Emergency Number)
Office Hours
Monday - Friday
7 a.m. - 3 p.m.
(No deliveries after 2 p.m.)
After-Hours Emergencies
Please call the Police Department's non-emergency line at 847-564-2060 for after hours emergencies including water main breaks, leaking meters, sewer back-ups or flooding.
Submit a Question or Service Request
Sign Up for Road Construction E-mail Updates