Cherry Lane Underpass Reconstruction

Cherry Lane Underpass Reconstruction

The Cherry Lane Underpass reconstruction is underway and running ahead of schedule. On Monday, May 22, the contractor finished Phase I of the project and began Phase II of the project on Tuesday, May 23. For Phase II of the project, one-way traffic will be flipped to the opposite side of the roadway with a one-way traffic lane open on the northern half of Cherry Ln., allowing westbound traffic to pass through the work area. Eastbound traffic will be re-routed using the current detour route.