General Information
Tentative Completion Date | July 15, 2021 (Tentative) |
Project Manager | Jim Huff, Project Manager 847-664-4122 |
Contractor | Builders Paving |
Awarded Contract Amount | $1,095,888 |
Funding Sources | Motor Fuel Tax Revenues/General Fund Revenues |
Special Note - Receive E-mail Updates About This Project
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2021.
Project Description
The Village of Northbrook proactively reviews the condition of its streets on a regular basis to identify problems and appropriate measures to correct them. This project involves resurfacing Founders Drive (from Kamp to Willow), Longmeadow Road (northern terminus to Lee) and Peeblebrook Road (both segments).Please note: A second phase of asphalt resurfacing will be completed as part of the Willow Creek project. Details on that section will be included on that project page.
Enabling Resolution
On Tuesday, April 27, the Village Board approved Resolution 2021-70, which awarded this contract to Builders Paving. Project Notices
On Thursday, May 13, the Village mailed an initial notice to all potentially impacted residents regarding this project. A copy of this notice can be found at this link.Project Locations
This project will focus resurfacing of Founders Drive (Kamp to Willow), Longmeadow (Lee to terminus) and Peeblebrook Road (both segments).Current Project Update
Friday, July 9
This week, the Village's contractor completed paving on Founders, Longmeadow and Pebblebrook and plans to complete pavement markings next week week.
Friday, June 25
Next week, the Village's contractor anticipates beginning paving work. Paving will begin on Founders Drive. Paving for Peeblebrook and Longmeadow will be announced next week as information becomes available.
Friday, June 18
Next week, the Village's contractor will grind each of the three streets included in Phase I work. Base patching will follow with paving beginning the following week.
Friday, June 11
This week, the Village's contractor completed all necessary pre-paving concrete work on Peeblebrook and Founders. Next week, the contractor plans to begin paving work.
Friday, June 4
The Village has received notice that the contractor will begin saw cutting, curb removal and replacement of Peeblebrook and Founders neek week.
Friday, May 28 - Work to begin on Peeblebrook and Founders Next Week
The Village has received notice from its contractor that preliminary work is scheduled to begin on Peeblebrook and Founders next week. This will include traffic control signage installation. Crews may also begin cutting curb by the end of the week.
April 27, 2021 - Contract Awarded
On Tuesday, April 27, the Village Board approved Resolution 2021-70, which awarded this contract to Builders Paving. Construction is anticipated to begin in June.
Communications
NotifyMe
The Village encourages those living in or immediately near this project to sign up to receive daily e-mails and/or text messages by using NotifyMe. Sign up at this link.
Other Communications
The Village will issue periodic written communications to those impacted by this project. However, for more frequent and updated contact, please subscribe to NotifyMe.
-
Public Works
Physical Address
655 Huehl Road
Northbrook, IL 60062
Phone: 847-272-4711Fax: 847-272-3629Emergency Phone: 847-564-2060 (After Hours Police Non-Emergency Number)
Office Hours
Monday - Friday
7 a.m. - 3 p.m.
(No deliveries after 2 p.m.)
After-Hours Emergencies
Please call the Police Department's non-emergency line at 847-564-2060 for after hours emergencies including water main breaks, leaking meters, sewer back-ups or flooding.Submit a Question or Service Request
Sign Up for Road Construction E-mail Updates