Willow Creek Subdivision Projects - 2021-2022

Completion Date November 30, 2021
Project Manager Aram Beladi, Project Manager, 847-664-4133
Contractor Mauro Sewer Construction (Water Main Work), Builders Paving (Asphalt Work)
Awarded Contract Amount $2,377,129 (Combined Cost for Phase 1, including work done outside of Willow Creek)
Funding Sources Bond Proceeds/Designated Revenue (MFT Funds)

Willow Creek Improvements Storyboard

There are multiple construction projects planned in the Willow Creek Subdivision in 2021 and 2022. To learn more about these projects and see maps of proposed improvements, please see the Willow Creek Improvements storyboard.

Special Note - Receive E-mail Updates About This Project

The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the projects.  If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2021.

Project Description:

The Willow Creek projects will be completed in two phases. The first phase will include water main improvements including the replacement of the original 1960's main on Longmeadow Drive, Elm Ridge Drive and Kingston Drive. Following completion of that work, asphalt roadway resurfacing will be completed on those same roadways. Phase two work will be completed in 2022 on the portions of Canterbury, Woodland and Wood located within the Willow Creek subdivision.

Please note: The asphalt contract for this project also includes work outside of the Willow Creek subdivision, including on Founders Drive, Longmeadow Road (off of Lee Road) and Peeblebrook Road. Updates for those projects can be found at this link.

Enabling Resolutions

On Tuesday, April 13, the Village Board approved Resolution 2021-49, which awarded the water main improvement work for this project to Mauro Sewer Construction, Inc. of Des Plaines. On Tuesday, April 27, the Village Board approved Resolution 2021-70, which awarded the asphalt work associated with this project to Builders Paving of Hillside.



Project Communications:

  1. On Friday, May 7, the Village mailed the construction notice for Phase I work. Please see a copy of this notice at this link.

Project Contacts

For questions regarding this project, please contact Aram Beladi, Project Manager. Mr. Beladi can be reached at 847-664-4133 or via the GONorthbrook system.

Current Project Update

Friday, July 16

The contractor will continue installing new watermain in the roadway on Kingston and Elm Ridge. 

Friday, July 2


The contractor will continue temporary restoration work on Longmeadow and Elm Ridge.  They will then begin grinding the roadway on Kingston and Elm Ridge to prepare for installation of the new water main on those roadways. 

Friday, June 25

The contractor will make final water main connections at the intersections of Canterbury and Elm Ridge as well as Pfingsten and Longmeadow and begin temporary restoration work on Longmeadow and Elm Ridge.  They will then begin grinding the roadway on Kingston and Elm Ridge to prepare for installation of the new water main on those roadways. 


Friday, June 18
This week, the Village's contractor will connect existing water service lines to the new water main, generally starting on Longmeadow near Pfingsten and heading eastward toward Elm Ridge. Affected homes will experienced temporary water outages as their home is being transferred to the new main. Notices will be delivered to homes prior to work taking place on their service line.

Friday, June 11
This week, the Village's contractor pressure tested and chlorinated the new water main on Elm Ridge. Once this new main is in service, the contractor will begin connecting residential water services to it. 

Friday, June 4

The contractor is continuing to install new water main in the roadway on Elm Ridge.  They will then begin installing fire hydrants and pressure testing the new water main.

Friday, May 28

The contractor is continuing to install new watermain in the roadway on Longmeadow.  They will then install watermain in the roadway on Elm Ridge from Longmeadow to Canterbury. 

May 21, 2021

The contractor intends to begin new watermain installation in the roadway starting on Longmeadow near Pfingsten.  Roadway watermain installation will proceed eastward towards Elm Ridge Dr.