2023 - Northbrook Highlands and Park Subdivision Projects
Completion Date | November 30, 2023 | |
Project Manager | Jim Huff, 847-664-4122 | |
Contractor | Mauro Sewer Construction, Inc. (Water Main Improvements) Brothers Asphalt Paving (Asphalt Rehabilitation Improvements) |
|
Awarded Contract Amount | $2,999,898 (Water Main Improvements) $1,272,450 (Asphalt Rehabilitation) |
|
Funding Sources | Bond Proceeds |
Special Note - Receive E-mail Updates About This Project
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the projects. If you are interested, please subscribe at this link. Updates will begin when the project commences in spring 2023.
Project Description:
This project will focus on the replacement of the original 1950's main on Butternut Lane, Penfold Place, and Summerton Place. Additionally, the original 1940’s main will be replaced on Ash Lane, Cedar Lane, and Peachtree Lane. This project will occur in conjunction with the scheduled street rehabilitation projects along these roads.
Enabling Resolutions
On Tuesday, March 14, 2023, the Village Board approved Resolution 2023-29, which awarded the contract for Water Main and Storm water improvements to Mauro Sewer Construction, Inc. of Des Plaines, Illinois.
On Tuesday, May 9, 2023 the Village Board approved Resolution 2023-97, which awarded the contract for asphalt rehabilitation improvements to Brothers Asphalt Paving, Inc of Addison, Illinois.
Project Communications:
On Tuesday March 7, 2023, the Village mailed the construction notices for this work. Separate Construction Notices were provided to both subdivisions impacted by this project.
The Construction Notice provided to the Northbrook Park Subdivision can be found at this link.
The Construction Notice provided to the Northbrook Highlands Subdivision can be found at this link.
Construction notices for the Asphalt Resurfacing work were mailed to residents in the Northbrook Highlands Subdivision on Monday, July 3, 2023 and can be found at this link.
Project Contacts
For questions regarding this project, please contact Aram Beladi, Assistant Village Engineer. Mr. Beladi can be reached at 847-664-4133 or via the GONorthbrook system
Current Project Update
Friday, September 1
This week the contractor paved the final surface of asphalt in the Highlands and Northbrook Park subdivisions.
In the next few weeks the contractor will continue to perform landscaping restoration and punch list items.
The project is now substantially completed. This will be the final weekly update. Thank you for your patience throughout construction of this project.
Friday, August 25
This week the contractor applied the base layer of asphalt pavement in the Highlands Subdivision. Additionally, the contractor performed asphalt removal and base patching in the Northbrook Park Subdivision.
Next week the contractor intends to pave the final surface layer of asphalt pavement in the Highlands Subdivision on Monday and Tuesday. They will pave the final surface layer of asphalt pavement in the Northbrook Park Subdivision on Wednesday. This schedule is weather dependent. Following the completion of paving, the contractor will continue to perform landscaping restoration.
Friday, August 18
This week the contractor completed asphalt removal and base patching in the Highlands Subdivision. They also substantially completed water main improvements in the Northbrook Park subdivision.
Next week the contractor will apply the first of two layers of pavement in the Highlands Subdivision. Additionally, the contractor will begin asphalt removal and base patching in the Northbrook Park Subdivision.
Friday, August 11
This week, the contractor completed spot curb replacement and accessibility improvements in the Highlands Subdivision. They also continued transferring water services on Penfold Place and Butternut Lane from the old water main to the new water main.
Next week, the contractor will begin asphalt removal and base patching in the Highlands Subdivision. They will also complete transferring water services on Penfold Place and Butternut Lane. Additionally, final water main connections will occur at the Dehne/Penfold intersection as well as the Dehne/Butternut intersection.
Friday, August 4
This week, the contractor began spot curb replacement in the Highlands Subdivision. They also continued transferring water services on Summerton Place and Penfold Place from the old water main to the new water main.
Next week, the contractor will perform spot curb replacement on the other side of the street in the Highlands Subdivision. They will also continue transferring water services on Penfold Place and Butternut Lane from the old water main to the new water main.
Friday, July 28
This week, the contractor continued landscaping restoration in the Highlands Subdivision. They also continued installing water main in the Northbrook Park subdivision on Penfold Place and Butternut Lane and began transferring water services from the old water main to the new water main on Summerton Place.
Next week, the contractor will begin spot curb replacement in the Highlands Subdivision. They will also continue transferring water services on Summerton Place and Penfold Place from the old water main to the new water main.
Friday, July 21
This week, the contractor completed concrete and temporary asphalt restoration in the Highlands Subdivision. They also continued installing the new water main in the Northbrook Park subdivision.
Next week, the contractor will complete landscaping restoration in the Highlands Subdivision. They also will continue installing water main in the Northbrook Park subdivision on Penfold Place and Butternut Lane.
Friday, July 14
This week, the contractor continued concrete and landscaping restoration in the Highlands Subdivision. They also continued installing the new water main in the Northbrook Park subdivision.
Next week, the contractor will complete concrete and landscaping restoration in the Highlands Subdivision along with performing a temporary asphalt patch in the roadway. They also will continue installing the new water main in the Northbrook Park subdivision on Summerton Place. Finally, they the contractor will begin installation of water main on Penfold Place, starting near Techny Road.
Friday, July 7
This week, the contractor began concrete and landscaping restoration in the Highlands Subdivision. They also began installing the new water main in the Northbrook Park subdivision, starting on Summerton Place near Techny Road.
Next week, the contractor will continue concrete and landscaping restoration in the Highlands Subdivision. They also will continue installing the new water main in the Northbrook Park subdivision on Summerton Place.
Friday, June 30
This week, the contractor performed final connections for the new water main and completed transferring service lines from the old water main to the new water main in the Highlands Subdivision.
Next week, the contractor will begin concrete and landscaping restoration. They will also begin installing the new water main in the Northbrook Park subdivision, starting on Summerton Place near Techny Road.
Friday, June 23
This week, the contractor began transferring service lines from the old water main to the new water main on Ash Lane and Peachtree Lane.
Next week, the contractor will complete transferring water service lines. They will also perform final connections for the new water main and begin removing the old water main from service.
Friday, June 16
This week, the contractor continued transferring service lines from the old water main to the new water main on Cedar Lane.
Next week, the contractor will begin transferring service lines from the old water main to the new water main on Ash Lane and Peachtree Lane.
Friday, June 9
This week, the contractor continued transferring service lines from the old water main to the new water main. Additionally, they completed bringing all of the newly installed water main into service.
Next week, the contractor will continue transferring service lines from the old water main to the new water main.
Friday, June 2
This week, the contractor began transferring service lines from the old water main to the new water main. Additionally, they continued bringing additional segments of the water main into service.
Next week, the contractor intends to continue transferring service lines from the old water main to the new water main. Additionally, they intend to continue bringing additional segments of the new water main into service.
Friday, May 26
This week, the contractor continued water main installation on Peachtree Lane and Ash lane and began bringing segments of water main into service in preparation for transferring services to the new water main.
Next week, the contractor intends to complete the remaining water main installation by completing the Ash Lane water main south of Peachtree and installing remaining hydrants. Additionally, they intend to begin transitioning service lines from the old water main to the new water main. Notices will be provided to alert residents prior to the start of service work.
Friday, May 19
This week, the contractor continued water main installation on Peachtree Lane and Ash Lane.
Next week, the contractor intends to continue water main installation on Peachtree Lane and Ash lane and begin bringing segments of water main into service in preparation for transferring services to the new water main.
Friday, May 12
This week, the contractor continued work on Peachtree Lane and began water main installation on Ash Lane .
Next week, the contractor intends to continue water main installation on Peachtree Lane and Ash lane.
Friday, May 5
This week, the contractor continued new water main installation on Ash Lane and connected the new main to the existing main by Dundee Road.
Next week, the contractor intends to continue work on water main installation on Peachtree Lane moving south. Additionally, the new main on Cedar Lane will be pressure tested and chlorinated to begin to bring it into service.
Friday, April 28
This week, the contractor finished work on water main installation on Cedar Lane and began work on water main installation on Ash Lane.
Next week, the contractor intends to continue work on water main installation on Ash Lane, moving south. On Monday May 1, 2023 the contractor intends to perform a water main shut off. Notices were sent to affected residents.
Friday, April 21
This week, the contractor continued work on water main installation on Cedar Lane.
Next week, the contractor intends to continue work on water main installation on Cedar Lane, moving south.
Friday, April 14
This week, the contractor began work on water main installation at the intersection of Ash Lane and Cedar Lane by Dundee Road.
Next week, the contractor intends to continue work on water main installation on Cedar Lane, moving south.
Friday, April 7
This week, the contractor began work grinding the asphalt roadway in locations where the trench will be dug for the proposed water main. Additionally, the contractor began work on mobilization, site layout, and tree protection.
Next week, the contractor intends to continue grinding the asphalt roadway. Additionally, the contractor intends to begin water main installation.
Friday, March 31
Next week, the contractor intends to grind the asphalt roadway in locations where the trench will be dug for the proposed water main. Additionally, the contractor will mobilize equipment and materials. Finally, the contractor intends to begin water main installation.
Friday, March 24
The contractor has informed the Village that they intend to begin work in the Highlands Subdivision (Ash, Cedar, and Peachtree), construction layout and staking is expected to occur next week. Project Updates for the Northbrook Park subdivision (Butternut, Penfold, Summerton) are expected to begin in late April or early May.