2022 - South Lane Water Main Improvements

General Information

Completion Date
June 24, 2022
Resident Engineer
Brian Parks, 630-824-7847
Project Manger
Michael Weller, 847-664-4132
Contractor
Mauro Sewer Construction, Inc., 847-803-2033
Awarded Contract Amount
$468,755
Funding Sources
Bond


Special Note - Receive E-mail Updates About This Project

The Village recognizes that this project will significantly impact residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the projects.  If you are interested, please subscribe at this link. Updates will begin when the project commences in May 2022.
 

Project Description

The South Lane Water Main Improvements project will include both water main replacement and asphalt resurfacing. The first part of the project will include water main improvements including the replacement of the original 1940's main on South Lane, while also looping the system to Driftwood Lane to further improve the system. Following completion of that work, asphalt roadway resurfacing will be completed on South Lane.

Enabling Resolution:

A full description of the project can be found as part of Resolution 2022-27, which awarded the project to the Village's contractor.

Construction Notification Letters:

On Friday, April 22 2022, the Village mailed the construction notice for water main work. Please see a copy of this notice at this link.

Project Contacts

For questions regarding this project, please contact Brian Parks, Resident Engineer. Mr. Parks can be reached at 630-824-7847. For additional questions please contact Michael Weller, Project Manager. Mr. Weller can be reached at 847-664-4132 or via the GONorthbrook system.
 

Current Project Updates

July 7, 2022

The project is complete. 

June 30, 2022

This week, the contractor intends to finish restoration work for the job site. 

June 24, 2022

This week, the contractor finished paving the road. Next week, the contractor intends to begin restoration work for the job site. 

June 16, 2022

This week, the contractor did not work on paving operations due to aggregate supply issues. Next week, the contractor is scheduled to mill and pave South Lane.

June 10, 2022

This week, the contractor finished the South Lane water main. Next week, the contractor’s schedule includes milling and paving of South Lane.

June 2, 2022

This week and next week, the contractor will continue water service connections. On Tuesday, June 7th, the contractor intends to perform a water main shutoff on South Lane to connect the new water main to the existing water main system on Voltz Road.

May 26, 2022

This week, the contractor intends to finish mainline work on South Lane, along with the connection on Driftwood Lane. On Tuesday, May 31st 2022, the contractor intends to begin service connections.

May 19, 2022

This week, the contractor intends to continue work on the water main connection between South Lane and Driftwood Lane. Next week, the contractor will continue water main work Driftwood Lane. On Monday May 23rd 2022, the contractor intends to perform a water main shutoff on Driftwood Lane to connect the new water main to the existing water main system.

May 12, 2022

This week, the contractor intends to finish water main installation on South Lane. Next week, the contractor intends to begin work on the water main connection between South Lane and Driftwood Lane. The contractor also intends to install fire hydrants on South Lane next week.

May 5, 2022

This week, the contractor intends to finish setting up temporary mail and parking areas, after which they intend to begin the installation of water main at the end of South Lane. Next week, the contractor will install water main starting on the southern end of South Lane.

April 28, 2022

Work on this project shall commence Monday, May 2nd 2022. The contractor intends to start by setting up temporary mail boxes and parking areas.  By the end of the week, the contractor will begin work on the water main connection to Driftwood Lane.

April 14, 2022

Work on this project is anticipated to begin in May 2022. Future updates will be posted here as they become available.