Elevator Permit

Please see below for permit submittal requirements associated with work requiring a permit, which would include but not be limited to the installation of new elevator, upgrades and/or modernization to existing elevators, decommissioning of an existing elevator, etc.

For information about current required upgrades or the bi-annual inspection program per the State of Illinois Elevator Safety Act.

Application Requirements

Application Fees & Deposits

  • Building Permit Application Fee - $325 per conveyance
  • Additional fees may apply at time of permit pick-up

Drawing/Construction Document Requirements

All plans must be stamped "Final Drawing Set."

  • Catalog cut sheets and specifications for parts being installed
  • Site Plan or Layout showing location of new and existing equipment

Required Inspections

Please visit the Elevator Inspection Program page for more information.

Additional Resources